Quick reference of core PMP/EVM formulas with an interactive Earned Value Management (EVM) calculator. Perfect for project managers, PMPs, and construction professionals.

Key Formulas (Reference)

  • CV = EV − AC
  • SV = EV − PV
  • CPI = EV / AC
  • SPI = EV / PV
  • EAC (typical) = BAC / CPI
  • EAC (schedule & cost) = AC + (BAC − EV) / (CPI × SPI)
  • ETC = EAC − AC
  • VAC = BAC − EAC
  • TCPI (to BAC) = (BAC − EV) / (BAC − AC)
  • TCPI (to EAC) = (BAC − EV) / (EAC − AC)